CPIM 2, 7.0, Mod 4 Sect A - C Flashcards | StudBud
Explore
/
CPIM 2, 7.0, Mod 4 Sect A - C
CPIM 2, 7.0, Mod 4 Sect A - C
10 terms
·
StudBud Administration
·
309 plays
Imported from external platform
Flashcards
10 cards
F
Practice quiz
P
Host live
L
Questions
10
Answers
1
The capacity check at the MPS level is called:
RCCP
Shop Floor Control
Resource Planning
CRP
2
Planning BOMs are used when it is impractical to forecast and master-schedule each unique end item.
True
False
3
Assuming no change in demand, if production is increased, backlog is also increased.
False
True
4
ATP can determine all of the following except:
Items can be shipped by customer's requested date
Product is available at time of order
Production can be increased
Items are available for single shipment
5
Time fences and time zones are techniques used to stabilize the MPS.
False
True
6
The Planning level for Master Scheduling is:
Shop Floor Execution
Product Family
End Item
Components
7
What are two Change Drivers relating to Demand?
Late delivery from suppliers
Defects in production
Sales and Marketing initiatives
Competition in the marketplace
8
Which of the following are Master Schedule Performance KPIs (check all that apply)
MPS aggregate performance
MPS lead time
MPS stability
MPS execution
9
Assuming no change in sales, when production is reduced, inventory is reduced as well.
False
True
10
The Planning level for S &OP is:
Shop Floor Execution
Product Family
Components
End Item