For Medical air systems, piping shall be hard-drawn, seamless copper tube type ___
ASTM B88
ASTM B88, B819, and B280
ASTM B280
ASTM B819
2
Bulk nitrous oxide system consists of more than _________ of gas.
3,200 lb.
20,000 ft2
3,200 psi
20,000 ft3
3
An assembly of equipment that holds a capacity of oxygen in use and storage greater than __ is defined as a Bulk System.
10,000 ft3
3200 Lbs.
3000 ft3
20,000 ft3
4
Who shall be responsible for developing an emergency plan in the event of medical air loss at a Category 2 facility?
Governing Body
Authority having jurisdiction
Head of maintenance
Facility staff
5
Medical air filters shall be sized for 100% of the system peak demand and be rated for a min of ___ efficiency at ___
100% at .1 micron or greater
98% at 1 micron or greater
95% at .5 micron or greater
98% at .01 micron or greater
6
In a medical gas system with emergency reserve, which alarm system(s) will activate when, or just before changeover?
Local and Master
Local
Area
Master
7
The minimum distance requirement at #3 is
10'
20'
5'
25'
8
Mechanical exhaust for central supply locations shall not be more than ____.
500 cfm
100cfm
50 cfm
72 cfm
9
Cryogenic fluid central supply systems up to the source valve, shall be installed in accordance with ______.
CGA - 99
NFPA 99
CGA - C7
NFPA 55
10
Item #4 is a ______ valve.
In-line
Riser
Service
Main line
11
Factory installed outlet tubes on station inlets shall be NOT less than ____ with 0.4 inch minimum inside diameter.
1/4 NPS
1/2 NPS
1/8 NPS
3/8 NPS
12
A medical air proportioning system shall have a min. of __ recorders for not less than 24 hrs.
3
2
4
1
13
A signal from each ___ shall be connected to the master alarm to indicate a problem is present with the source equipment
Area Alarm
Local Alarm
Pressure Switch
Anesthetizing
14
Which of these components are required at the connection to an emergency oxygen supply connection (EOSC).
Final line filter
4 alarm connection points to monitor the truck
A single check valve
Line Pressure Regulator
15
Gas produced by evaporation from in a bulk container system shall enter the supply ___ of the final line regulator.
Downstream
Upstream
Downstream of the filter
Upstream of the filter
16
Area 2 would be classified as a _________.
None Apply
Critical care area
Anesthetizing area
General Patient Care Area
17
Which of the following filler metals shall be used to braze copper-to-copper joints in medical gas/vacuum piping?
BAg series
BNi series
BAu series
BCuP series
18
Manifolds for gas cylinders shall actuate a(n) ___ signal and activate a indicator at all ___ alarm panels at changeover
Local, Master
Local, Area
Master, Area
Area, Master
19
In a non-anesthetizing Cat. 1 space, on which side of a zone valve shall the area alarm sensor be located?
Upstream
Station Outlet/Inlet
Source
NFPA does not Specify
20
Vacuum piping for ___ shall be connected separately from the medical surgical system directly to the receiver tank.
A location requiring seismic restraint
Each WAGD system
The standing vacuum test
A teaching laboratory
21
How many hours must the medical air compressor system be operating normally before air quality test can be performed?
2
24
8
12
22
In those portions of the system intended to handle oxygen at greater than 350 psi, the hose shall not contain ____
Copper Materials
Brass Materials
Polymeric Materials
Stainless Steel
23
Which of the following conditions must be met so medical gas and vacuum systems are installed by non-certified personnel
The installer must be an employee of an authorized Medical Gas contractor
Installation by anyone other than 6010 certified personnel is NOT permitted
Installer certified to ASSE 6010 must be present to oversee installation
An ASSE 6020 inspector is present on the job to inspect the installation
24
The minimum distance requirement at #4 is
25'
15'
10'
20'
25
The pressure in the main line of each medical gas system, shall be monitored at the _______ alarm
Local
Master
Local and Area
Area