PMP Exam Questions (Framework & Integration) Flashcards | StudBud
Explore
/
PMP Exam Questions (Framework & Integration)
PMP Exam Questions (Framework & Integration)
10 terms
·
StudBud Administration
·
380 plays
Introducing the basics of #pmp
Flashcards
10 cards
F
Practice quiz
P
Host live
L
Questions
10
Answers
1
Fill in the blank: _______________means developing in steps and continuing by increments.
Waterfall Development
Progressive Management
Iterative Elaboration
Progressive Elaboration
2
In a functional organization, what's the role of project sponsor during execution process??
Providing Project Status to Management
Communicating with the project stakeholders
Helping the PM to resolve issues
Managing Integrated Change Control Process
3
Which of the following is an Enterprise Environmental Factor?
Change Control Procedures
Configuration Management Knowledge base
Historical Information
Commercial Databases
4
The following is not an input to the Develop Project Charter Process..
Enterprise Environmental Factor
Expert Judgment
Statement of Work
Business Case
5
Which of the following, normally provides the summary milestone schedule..
Business Case
Project Charter
Project Requirements Document
Project Scope Statement
6
A PM uses the following management skills to coordinate towards accomplishing a goal, EXCEPT
Public speaking
Negotiating
Presentation
Active listening
7
PM's primary professional responsibility is towards...
The Project Sponsor
All Stakeholders
The performing organization
Customers
8
Which of the following is the project manager always responsible for...
Selecting appropriate processes for the project
Prioritizing projects based on business needs
Obtain the project's profit margin
Writing performance reports for project resources
9
The following tool/technique includes mind mapping and affinity diagram...
Stakeholder analysis techniques
Observation techniques
Group decision making techniques
Group creativity techniques
10
Organizational Process Assets that are updated during the Close Project or Phase process are:
Project Management Plan, Risk Register
Project Charter, Business Case
Project Charter, Resource Calendar
Project Management Plan, Expert Judgment