What is the free float for Activity H?
2
0
5
3
2
Project is under budget when the Cost Variance is a
Negative
Positive
3
What is it called when the contractor pays out more money in a particular month than cash received by the owner?
Negative clash flow
Upside down payment structure
Contractor financed payments
Creative financing
4
What is the free float for Activity I?
1
Inadequate information provided
-1
0
5
The goal of Pull Planning is to get precedence work done as responsibly close to when subsequent work can begin.
False
True
6
Lag is any duration required between finishing one activity and starting another (e.g. cure time).
True
False
7
Project is ahead schedule when Schedule Variance is a
Postive Value
Negative Value
8
Crashing activities with 2 days of free float by 2 days will reduce the total project duration by 2 days
True
False
9
Least costly way to divert river water during dam construction?
Siphon
Cofferdam
Buckets
Electric Pump
10
Just-in-Time delivery management results in a reduced area for on-site storage?
False
True
11
What is the total float for Activity H?
5
Inadequate info provide.
8
10
12
Backfloat is calculated during which scheduling calculation?
None of the above
Resource leveling
Resource allocating
Forward & Backward Pass
13
What statistical calculation is used when leveling the daily resource count?
Duration Coefficient
Standard Deviation
Average
Variance
14
_________is a math calculation & process which distributes limited craft population
Schedule crashing
Resource leveling
Resource allocation
Schedule optimization
15
The allocation of constrained resources may result in the duration of the project being extended.
False
True