Quiz 3 SOBs
Quiz 3 SOBs
89 terms
·
StudBud Administration
·
11 plays
Imported from external platform
Flashcards
89 cards
F
Practice quiz
P
Host live
L
Questions
89
Answers
1
Bob revised the cost estimate and it looks like he will not meet the "threshold" of the cost KPP. Bob deviated.
True
False
2
Performance Work Statement (PWS) is comparable to a Statement of Work (SOW) more so than Statement of Objectives (SOO)
True
False
3
List the three phases in the 7-step process for the Acquisition of Services pathway
Execute
Develop
Plan
Deter
Engage
Prepare
4
What's going on here in the red boxed area?
Integration Phase has not started
Integration Phase has started
5
When calculating Schedule or Cost Performance Index, a CPI/SPI > 1 indicates what?
Behind Schedule (Inefficient)
Over Budget (Inefficient)
Off Target
Under Budget (Efficient)
Ahead of Schedule (Efficient)
On Target
6
"Portfolio" execution
Program Executive Officers (PEO)
Secretary of the Air Force (SAF)
Office of the Secretary of Defense (OSD)
Program Managers (PM)
Joint Chiefs of Staff (JCS)
President
7
When calculating Schedule or Cost Performance Index, a CPI/SPI < 1 indicates what?
Ahead of Schedule (Efficient)
Under Budget (Efficient)
On Target
Off Target
Behind Schedule (Inefficient)
Over Budget (Inefficient)
8
Describe program deviation
Revised CSP Estimate indicates a CSP threshold will be breached
Failure to meet APB threshold
CSP (KPP) threshold breaches
90 days to recover or recommend APB revision to MDA
9
Responsible for passing Defense Appropriations Act. Assigns specific dollar amounts to each program.
Acquisition Program Baseline (APB)
Armed Services Committees
Budget Committees
Government Accountability Office (GAO)
Congressional Budget Office (CBO)
Appropriation Committees
10
What's a Supply?
worker
computer
driver
pilot
"in" the boxes
boxes themselves
11
Bob revised the schedule and it looks like he will not meet the "objective" finish date estimate. Bob deviated.
True
False
12
Captures the current state and the history of the technical baseline & serves as "central reference point" for models
Digital Threads
Authoritative Sources of Truth (ASoT)
Digital Engineering
Model-Based System Engineering (MBSE)
Digital Twin
13
identify the level of oversight required (Cost or MDA Interest)
Acquisition Categories (ACATs)
Program Reporting
Acquisition Decision Memorandum (ADM)
Acquisition Program Baseline (APB)
14
Describe the overall purposes of the Air Force Life Cycle Management Center (AFLCMC)
Nuke
Installation
Research
Test
Air Force Systems
Sustainment
15
Space Systems
USD A&S
Space Systems Command (SSC)
SAF/AQ & SQ
16
What's going on here in the red boxed area?
Did work planned for this month
Did work not planned for this month
17
Details the integrated strategy & overarching T&E objectives for a program
Lead Development Test Organization (LDTO)
Statement of Capability (SOC)
Program Introduction Document (PID)
Contractor
Air Force Operational Test and Evaluation Center (AFOTEC)
Test & Evaluation Master Plan (TEMP)
18
Explain the importance of security assistance and FMS
Responsible for continuous supervision & direction of funds
Helps allies tackle economic and political instability
Assists allies in acquiring, maintaining, & employing self-def capes
Allows for the transfer/sale of US military articles and services
19
List who to contact if you have an ethics question
Judge Advocate General (JAG)
Office of Government Economics (OGE)
DoD designated ethics official
Office of Government Ethics (OGE)
20
"Link models and create an authoritative source of truth." Integrate and transform disparate data
Digital Twin
Authoritative Sources of Truth (ASoT)
Model-Based System Engineering (MBSE)
Digital Engineering
Digital Threads
21
Facilities that provide the DoD organic capability to overhaul, repair, modify, & sustain new & existing weapons systems
Organic Support
Performance-Based Logistics (PBL)
Depot Source of Repair (DSOR)
Product Support
Air Logistics Complexes (ALC)
Contractor Logistics Support (CLS)
22
create and manage the strategy for T&E for the life of each program. CDT & Op Test Org
Developmental Test and Evaluation (DT&E)
Operational Test and Evaluation (OT&E)
Test and Evaluation Master Plan (TEMP)
Integrated Test Teams (ITT)
23
What's a Service?
worker
driver
pilot
boxes themselves
"in" the boxes
computer
24
Test and Evaluation, Developmental, Demonstrate a new capability,Instrumentation “Two = Test”
Permanent (P)
Temporary (T-2)
Temporary (T-1)
25
Continuous & collaborative activities, establishes/maintains readiness & operational capes of systems entire lifecycle
Air Logistics Complexes (ALC)
Contractor Logistics Support (CLS)
Organic Support
Product Support
Performance-Based Logistics (PBL)
Depot Source of Repair (DSOR)
26
Define Diminishing Manufacturing Sources and Material Shortages (DMSMS)
The loss or impending loss of manufacturers of items
Product support value chain from design through disposal
Ensure designs are supported and the support is designed
Suppliers that may endanger a weapon system’s support capability
27
"intangible" but identifiable
Service
Supply
28
To specify outcome performance goals
Performance-Based Logistics (PBL)
Contractor Logistics Support (CLS)
Product Support
Organic Support
Air Logistics Complexes (ALC)
Depot Source of Repair (DSOR)
29
What's going on here in the red boxed area?
Ahead of Schedule & Under Budget
Behind Schedule & Over Budget
30
When calculating Schedule or Cost Variance, a (-) Negative number indicates what?
Behind Schedule
Ahead of Schedule
Over Budget
Under Budget
31
SAF/AQ is a major player in FMS
True
False
32
monitor the economy & conduct ICEs for legislation
Armed Services Committees
Budget Committees
Congressional Budget Office (CBO)
Government Accountability Office (GAO)
Acquisition Program Baseline (APB)
Appropriation Committees
33
Types of conflicts of interest that could lead to common ethics violations
Procurement Information
Financial Conflicts
Gifts from Contractors
Impartiality Issues
Employment Restrictions
Fundraising
34
Describe the overall purposes of the Air Force "Research" Lab (AFRL)
Test
Research
Nuke
Installation
Air Force Systems
Sustainment
35
Describe the overall purposes of the Air Force "Test" Center (AFTC)
Research
Installation
Test
Nuke
Sustainment
Air Force Systems
36
Identifies the requirements for the test program
Statement of Capability (SOC)
Program Introduction Document (PID)
Lead Development Test Organization (LDTO)
Contractor
Test & Evaluation Master Plan (TEMP)
Air Force Operational Test and Evaluation Center (AFOTEC)
37
Modification is Temporary or Permanent alteration to a fielded system, equipment, or material: Creates a change to F3I
True
False
38
Set revenue targets & outlays. Study effects of proposed legislation.
Acquisition Program Baseline (APB)
Budget Committees
Congressional Budget Office (CBO)
Government Accountability Office (GAO)
Armed Services Committees
Appropriation Committees
39
(1/2) List the major players involved in FMS
SEO
Congress
DSCA
SecState/DoS
President
SecDEF/DoD
40
identify the DoD ethics regulation
DoD 5500.7-R, Joint Economy
DoD 7500.5-R, Joint Ethics
DoD 7500.5-R, Joint Economy
DoD 5500.7-R, Joint Ethics
41
DT&E at their facilities, OT&E only support how they would in war!
Test & Evaluation Master Plan (TEMP)
Contractor
Lead Development Test Organization (LDTO)
Air Force Operational Test and Evaluation Center (AFOTEC)
Statement of Capability (SOC)
Program Introduction Document (PID)
42
Official record of MDA "decisions" for Milestones/Decision Points
Acquisition Program Baseline (APB)
Acquisition Decision Memorandum (ADM)
Program Reporting
Acquisition Categories (ACATs)
43
"tangible" asset or product
Supply
Service
44
When calculating Schedule or Cost Variance, a (+) Positive number indicates what?
Under Budget
Over Budget
Ahead of Schedule
Behind Schedule
45
support that is contracted out
Air Logistics Complexes (ALC)
Product Support
Organic Support
Performance-Based Logistics (PBL)
Depot Source of Repair (DSOR)
Contractor Logistics Support (CLS)
46
Describe the overall purposes of the Air Force "Sustainment" Center (AFSC)
Nuke
Sustainment
Installation
Research
Test
Air Force Systems
47
Permanent, Operational, Adds capability and/or addresses a deficiency, Consider impacts across the entire fleet
Temporary (T-2)
Temporary (T-1)
Permanent (P)
48
DoD must maintain a core logistics capability/controlled source of tech competence & resources for surge operations
Core Law
50/50 Law
49
Funding for services is the responsibility of...
the buyer
the user
the MAJCOM
the supplier
50
MDA & "DAF" acquisition policy
Space Systems Command (SSC)
SAF/AQ & SQ
USD A&S
51
LDTO’s response to PID
Program Introduction Document (PID)
Contractor
Air Force Operational Test and Evaluation Center (AFOTEC)
Lead Development Test Organization (LDTO)
Test & Evaluation Master Plan (TEMP)
Statement of Capability (SOC)
52
integrated digital approach, uses "authoritative" sources of sys data & models across disciplines/support lifecyce
Digital Engineering
Digital Threads
Authoritative Sources of Truth (ASoT)
Digital Twin
Model-Based System Engineering (MBSE)
53
Documents agreement with MDA to achieve CSP
Acquisition Decision Memorandum (ADM)
Acquisition Program Baseline (APB)
Acquisition Categories (ACATs)
Program Reporting
54
Responsible for passing NDAA. Authorizes programs & sets funding limits
Government Accountability Office (GAO)
Armed Services Committees
Congressional Budget Office (CBO)
Acquisition Program Baseline (APB)
Budget Committees
Appropriation Committees
55
(3/3) All of these are Integrated Product Support (IPS) Elements "EXCEPT"
Computer Resources
Diminishing Manufacturing Sources and Material Shortages (DMSMS)
Facilities
56
Describe the purposes of T&E
Evaluates design approaches
Mature system designs
Provide the acquisition community w/knowledge to improve system performance
Identify & resolve deficiencies early
Provide user community w/knowledge to optimize system ops&sustainment
Manage risks
57
"Program" execution
Office of the Secretary of Defense (OSD)
Program Executive Officers (PEO)
President
Secretary of the Air Force (SAF)
Joint Chiefs of Staff (JCS)
Program Managers (PM)
58
Describe the overall purposes of the Air Force "Installation" and Mission Support Center (AFIMSC)
Nuke
Research
Air Force Systems
Sustainment
Test
Installation
59
(2/3) All of these are Integrated Product Support (IPS) Elements "EXCEPT"
Support Equipment/Automatic Test Systems (SE/ATS)
Packaging, Handling, Storage, & Transportation (PHS&T)
Franchises
Manpower & Personnel
Training
Technical Data Management/Technical Orders(TDM/TOs)
60
emphasizes performance-based concepts such as desired service outcomes and performance standards (“what” not “how”)
Statement of Work (SOW)
Requirements Approval Document (RAD)
Performance Work Statement (PWS)
Statement of Objectives (SOO)
61
Special Operations, Operational, Adds capability, Minimum logistical support changes “One = Operation”
Temporary (T-2)
Temporary (T-1)
Permanent (P)
62
Realistic test environment
Operational Test and Evaluation (OT&E)
Test and Evaluation Master Plan (TEMP)
Developmental Test and Evaluation (DT&E)
Integrated Test Teams (ITT)
63
Approves "Joint" requirements
Joint Chiefs of Staff (JCS)
Secretary of the Air Force (SAF)
Program Executive Officers (PEO)
President
Office of the Secretary of Defense (OSD)
Program Managers (PM)
64
military and government support
Performance-Based Logistics (PBL)
Air Logistics Complexes (ALC)
Contractor Logistics Support (CLS)
Depot Source of Repair (DSOR)
Organic Support
Product Support
65
No more than 50% funds made available in FY to a military department for depot-level mx, may be used to contract non-gov
Core Law
50/50 Law
66
Conducts all IOT&E, QOT&E and FOT&E
Contractor
Program Introduction Document (PID)
Test & Evaluation Master Plan (TEMP)
Air Force Operational Test and Evaluation Center (AFOTEC)
Statement of Capability (SOC)
Lead Development Test Organization (LDTO)
67
What's going on here in the red boxed area?
EV Data is fine
EV Data disconnect
68
Goal of Acquisition Logistics
More Supportable
More Reliable
Reduce Life-Cycle Costs (LCC)
Easily Maintained
69
approach to engineering that uses "mathematical models" tech baseline def includes requirements, analysis, design, capes
Digital Threads
Authoritative Sources of Truth (ASoT)
Model-Based System Engineering (MBSE)
Digital Twin
Digital Engineering
70
Describe the Requirements Approval Document (RAD)
impact of non-approval
defines a tangible asset
describes services required by the using organization
budget requested to satisfy requirement
contract timeframe
period of performance
71
A purpose of T&E: provide acquisition community with knowledge to improve the system performance "BEFORE" production
True
False
72
a one-to-one digital model of a real world-system that’s tied to its physical counterpart through a data feedback loop
Model-Based System Engineering (MBSE)
Digital Threads
Digital Engineering
Authoritative Sources of Truth (ASoT)
Digital Twin
73
"Timely" assessment & communication of information for a program’s health & status
Acquisition Program Baseline (APB)
Acquisition Categories (ACATs)
Program Reporting
Acquisition Decision Memorandum (ADM)
74
Defense policies & budget. Organize, train, and equip. Oversees the DAS
Program Managers (PM)
Office of the Secretary of Defense (OSD)
Secretary of the Air Force (SAF)
Program Executive Officers (PEO)
President
Joint Chiefs of Staff (JCS)
75
(1/3) All of these are Integrated Product Support (IPS) Elements "EXCEPT"
Product Support (PS) Management
Sustaining Engineering
Design Interface
Supply Support
Poking, Hopping, Sleeping, & Friendship (PHS&F)
Maintenance Planning & Management
76
MDA & "DoD" acquisition policy
SAF/AQ & SQ
USD A&S
Space Systems Command (SSC)
77
Identify the major responsibilities of AF Program Executive Officer for Combat and Mission Support (AFPEO/CM)
acquisition governance
Comparable to a Statement of Objectives (SOO)
processes to ensure effective implementation of policies for the DAF
establish managment structures
78
At Milestone A, anticipate needs At Milestone B organic/contractor determined+assign DoD facility DoD level(SORA+DMI)
Product Support
Depot Source of Repair (DSOR)
Performance-Based Logistics (PBL)
Contractor Logistics Support (CLS)
Air Logistics Complexes (ALC)
Organic Support
79
Funding sources vary depending on the requirements source
False
True
80
(2/2) List the major players involved in FMS
SCO
SAF/AQ
AFSAC
SAF/IA
AFSAT
SAPM
81
Tony agreed to achieve CSP with the MDA but needs to change the APB & won't meet a threshold. Tony did NOT deviate.
True
False
82
Describe the overall purposes of the Air Force "Nuclear" Weapon Center (AFNWC)
Air Force Systems
Installation
Research
Test
Sustainment
Nuke
83
Evaluates design approaches
Operational Test and Evaluation (OT&E)
Test and Evaluation Master Plan (TEMP)
Integrated Test Teams (ITT)
Developmental Test and Evaluation (DT&E)
84
examines how appropriated funds are used
Government Accountability Office (GAO)
Appropriation Committees
Acquisition Program Baseline (APB)
Armed Services Committees
Budget Committees
Congressional Budget Office (CBO)
85
National security and fiscal policies
Office of the Secretary of Defense (OSD)
Program Executive Officers (PEO)
Secretary of the Air Force (SAF)
President
Joint Chiefs of Staff (JCS)
Program Managers (PM)
86
Is the Death Star Ahead or Behind Schedule? (SV=BCWP-BCWS, Design=1M, Space Lift=4M, Reactor=1M, Laser=2M, BCWS=7M)
Ahead (SV = $1M)
Behind (SV = -$2M)
Behind (SV = $1M)
Ahead (SV = -$2M)
87
Lead government entity qualified to conduct and be responsible for overseeing DT&E
Test & Evaluation Master Plan (TEMP)
Contractor
Air Force Operational Test and Evaluation Center (AFOTEC)
Program Introduction Document (PID)
Lead Development Test Organization (LDTO)
Statement of Capability (SOC)
88
under secdef. Over AF policy
President
Secretary of the Air Force (SAF)
Program Executive Officers (PEO)
Office of the Secretary of Defense (OSD)
Joint Chiefs of Staff (JCS)
Program Managers (PM)
89
Describe the goal of life cycle logistics and its importance
The loss or impending loss of manufacturers of items
Suppliers that may endanger a weapon system’s support capability
Product support value chain from design through disposal
Ensure designs are supported and the support is designed