Chapter 8. Project Cost Management
1 / 18
Question 3.
How is Cost baseline calculated?
A
Contingency Reserves + Management Reserves
B
Project Cost Estimates + Contingency Reserves + Management Reserves
C
Project Cost Estimates + Contingency Reserves
D
None of the above